This article explains how to make sure actual charges are posted using the correct budget headings.
- You’ll either use the Purchase Ledger Transactions screen or the Proposed Invoices screen to post your charges.
- This depends on whether you’re using the In-Tray or your contractors are submitting invoices via Blockworx (the Contractor Portal).
This article covers both methods.
Adding Charges in Purchase Ledger Transactions
To ensure accurate
reporting, always select the correct
Budget Heading when posting invoices. This allows charges to be matched with the appropriate items in your budget. It's especially important for developments set to invoice on a budgeted basis.
A budget heading must be selected in the Purchase Invoice Posting Details section for each charge on the invoice. Be sure to select either an individual client or an apportionment, depending on how the charge should be applied:
You must select a Budget Heading to post the transaction, even if the charge isn’t intended to be part of the budget. This applies to any posting made to a development with its accounting basis set to Budgeted.
If you are adding an invoice that is not included in the budget, you can flag the charge as
Immediate:

Then, when
processing the Hold File, you can choose to process only charges marked
Immediate, allowing you to invoice the client(s) for this charge alone by running an
Amended Account. Consult
this article for more details.
You don’t have to mark the invoice as
Immediate, you can leave it as
Next invoice run to include it the next time you run your
Amended Accounts.
Posting Proposed Invoices from In-Tray
If an invoice has been submitted via the In-Tray, you’ll add the necessary details through the Post Proposed Invoice screen:
Fill in all required fields. Then, in the Budget Heading column at the bottom of the screen, select the appropriate heading from the drop-down list for each charge. Continue posting as normal.
This step is mandatory for developments invoiced on a budgeted basis.
Posting Proposed Invoices from the Blockworx/Contractor Portal
Invoices submitted by contractors through the Blockworx/Contractor Portal will appear directly in the Proposed Invoices screen.
When posting, you can check and edit the details. Make sure to select the correct Budget Heading at the bottom before continuing:
An invoice can’t be posted without a heading, ensuring charges match the budget at reconciliation.
Additional Options
If the "Budget Only Post to Allocated Headers" system option is enabled, you’ll only be able to select Budget Headings that are already included in the budget for the development. These are the only headings that will appear in the drop-down list, preventing charges from being posted to incorrect or unrelated headings.
Posting Charges to the Hold File
You can post charges to the Hold File and release them as usual. These charges will appear under the client’s Charge Transaction tab until the budget reconciliation is carried out at the end of the budget period:
If the total charges against a budget heading are within the amounts budgeted, the client will have already paid for them, depending on the charge date code and based on the budget invoice(s) sent earlier.
If the total charges exceed the budgeted amount, the client will have a shortfall to pay at reconciliation.
If the charges are lower than the budgeted amount, the client will be due a refund at reconciliation.
For more details on Budget Reconciliations check
this article.